PROJECT UPDATE
Henderson Site Services are currently progressing the Refresco (Durham) Pet Bottling Project in conjuction with not only the client and end user but also the various other installation companies within the project such as GEA and TETRAPAK. We are working closely with all parties expending circa 1200 manhours per week to ensure a seamless interface with all supplied plant and processes and are carrying out works ranging from the full installation of all process and service pipework including the thermal insulation to the design, manufacture and installation of a 2m wide access gantry stretching the full 60m length of the production hall and standing 3m high.